Earned Value Management explained in five minutes
Most project status reports answer one question: how much have we spent? That is useful, but it says nothing about whether the money bought the progress it should have. Earned Value Management (EVM) closes that gap by comparing four numbers.
The four numbers
- Planned Value (PV) — the budgeted value of the work you planned to have done by now.
- Actual Value (AV) — the budgeted value of the work you have actually completed.
- Planned Cost (PC) — what the work you planned to have done by now was budgeted to cost.
- Actual Cost (AC) — what that completed work actually cost.
A simple example
A project has a budget of 1,000,000 kr over ten sprints. After four sprints the plan said 40% should be done, so PV = 400,000 kr, and the cost plan expected PC = 380,000 kr to have been spent. In reality 30% is done, so AV = 300,000 kr. The team has spent AC = 360,000 kr.
Looking only at spend (360,000 against a planned 380,000), the project even seems to be under budget. EVM tells a different story.
Two variances that tell the truth
- Time: AV against PV. Value worth 300,000 kr has been delivered against 400,000 kr planned — only 75% of the plan.
- Cost: AV against AC. Work worth 300,000 kr has cost 360,000 kr — 60,000 kr too much.
So the project is behind and over budget — something a spend-only report would have hidden.
Forecasting the finish
If things carry on like this, every krone of value costs 1.20 kr. The project then finishes at roughly 1,000,000 × 360 / 300 ≈ 1,200,000 kr. That is a number a steering committee can act on today, not at the end of the project.
Getting started
You do not need a heavy toolchain. You need a baseline, a way to measure completion consistently (for example, done user stories per sprint) and actual cost from your time registration. ATLAS is built to do exactly that — or book a demo and we will show you with your own numbers.